PS2007 Timesheet and the 38 Hour working week

G

Gordon

I have a 38 hr working week (7.6 hrs per day) users pretty anal about it.
I am not sure the EPM solution handles this very well.

I have specified working times in the MS Project Prof template 38 hrs week
and 7.6 hrs per day: In MS Project Professional this works like a dream. If I
specify a task of 4 days duration, it automatically calculates the work
effort at 30.4 hrs.

However when I publish this project onto the server there is a problem in
the Timesheet view:

Timesheet View:

For some reason the planned effort is spread across 8hrs (trimming the start
and end day). So 30.4hrs is split over 4 days as (7, 8, 8, 7.4.).

Ideally I was looking for the time sheet to display (7.6, 7.6, 7.6, 7.6)

In the Server Settings > Timesheet Settings I have specified time sheet day
as 7.6 hrs, and standard worksheet week as 38hrs.

Other Timesheet Setttings:

Outlook Display: Billable,Non-Billable , and Scheduled hours (selected)
Timesheet will use standard overtime and non billable time tracking
(un-selected)
By Default timesheet will be created by using current task assignments.
The Default timesheet tracking units are set to Days.



Any pointers will be of great help.
 
J

Jackson T. Cole

Not sure of the details, but you need to ensure your project calendar is
in agreement with the Project Professional Calendar option of 38 hours per
week. I can't point you a specific reference, either, sorry. This is an
area I don't think too many people, even the "experts", have a handle on! :>)
 