L
Langhorne
I was disappointed to see that SP1 didn't address what I consider to be a
glaring omission in how Project Server 2007 handles timesheets -- a column
totalling the effort for the week by task and by project. It's right there
plain as day in PS03, both when viewing My Tasks and printing as a timesheet.
When PS07 separated tasks from timesheets, this feature was removed from
both.
How are people using PS07 timesheets without knowing what the total for the
timesheet period is? Any workarounds, hot fixes, 3rd-party add-ons? This
seems like such a basic function for a timesheet that I still don't
understand why it was removed.
As a side note, I also miss PS03's ability to collapse a project's subtasks
and just list the project total on the timesheet.
glaring omission in how Project Server 2007 handles timesheets -- a column
totalling the effort for the week by task and by project. It's right there
plain as day in PS03, both when viewing My Tasks and printing as a timesheet.
When PS07 separated tasks from timesheets, this feature was removed from
both.
How are people using PS07 timesheets without knowing what the total for the
timesheet period is? Any workarounds, hot fixes, 3rd-party add-ons? This
seems like such a basic function for a timesheet that I still don't
understand why it was removed.
As a side note, I also miss PS03's ability to collapse a project's subtasks
and just list the project total on the timesheet.