PS2007 - what replaced work groups?

M

Michelle Hotz

We are currently implementing PS2007 to replace Project Central. In Project
2000 we created custom fields that we added to workgroup messages that sent
over to Project Central. I don't see work groups in Project 2007 - is there
a way to send custom field data to Project Server?

Michelle
 
D

Dale Howard [MVP]

Michelle --

The Project Server administrator creates custom enterprise Fields and Lookup
Tables using the PWA interface. Hope this helps.
 