[PS2007] - Wierd behaviour of Remaining Work in PWA

G

godrid

Hi,

I am using PS2007-SP1, and I notice that when I update remaining work for a
fixed unit task using PWA, the actual work will also be affected while the %
work completed remains constant. This behaviour is correct when I do it on
Project Professional which the actual work will remain as previous but % work
completed changes when I modify the remaining work.

Regards
Godrid
 
G

godrid

Hi Paul,

The problem seems to be fixed after I applied hotfix KB941426.

Thanks & Best Regards
Godrid
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top