Hi,
I am using PS2007-SP1, and I notice that when I update remaining work for a
fixed unit task using PWA, the actual work will also be affected while the %
work completed remains constant. This behaviour is correct when I do it on
Project Professional which the actual work will remain as previous but % work
completed changes when I modify the remaining work.
Regards
Godrid