R
Ryan
Hello
I have a very frustrating situation. I have 2 projects in Project Server
2007 (SP1, Dec 08 Cumulative Patch) that have had thier actual work reported
by resources, 1) be split into a timephase format with odd fractions on each
day (i.e. 2.67hrs which no one would actually enter several days in a row),
and 2) moved out into 2042 and 2043.
Has anyone seen this and know why it's happening and how to stop/correct it?
Thanks,
Ryan Miller
I have a very frustrating situation. I have 2 projects in Project Server
2007 (SP1, Dec 08 Cumulative Patch) that have had thier actual work reported
by resources, 1) be split into a timephase format with odd fractions on each
day (i.e. 2.67hrs which no one would actually enter several days in a row),
and 2) moved out into 2042 and 2043.
Has anyone seen this and know why it's happening and how to stop/correct it?
Thanks,
Ryan Miller