PS2K7 Is moving actual time entered into future days/years

R

Ryan

Hello

I have a very frustrating situation. I have 2 projects in Project Server
2007 (SP1, Dec 08 Cumulative Patch) that have had thier actual work reported
by resources, 1) be split into a timephase format with odd fractions on each
day (i.e. 2.67hrs which no one would actually enter several days in a row),
and 2) moved out into 2042 and 2043.

Has anyone seen this and know why it's happening and how to stop/correct it?

Thanks,

Ryan Miller
 
G

Gary L. Chefetz

N

nut

Gary L. Chefetz wrote on 03/06/2009 06:03 ET
Ryan

More than likely you are experiencing a known issue that will be fixed i
the April CU. Until this releases, you will need to have your PMs do som
manual cleanup on their plans each time this occurs


Gary L. Chefetz, MV
MSProjectExpert
Project Server Consulting: http://www.msprojectexperts.co
Project Server Training: http://www.projectservertraining.co
Project Server FAQS: http://www.projectserverexperts.co
Project Server Help Blog: http://www.projectserverhelp.co


"Ryan" wrote in messag
news
Hi Gary
I'm experiencing the exact same problem, also outlined a

http://www.eggheadcafe.com/software/aspnet/29710537/problem-with-work-contour.asp

My project 2007 server is up to date with all patches; any input you ca
provid
on how to resolve this issue would be most helpful, as this is reall
frustrating

Thanks in advance
Nathan.
 