Skaarj
Hello,
maybe I did a mistake when asking for help for writing "working data"
into an assignment and I really meant "time phased data". So I wanna
be more precise and would like to ask you for help to write time
phased data into assignments.
An example: I create an assignment with work = 0h and in a second step
I want to set work from March 12th to 16th and March 26th to 30th with
8h per day. After studying the SDK I found that the method
"SetAssignmentWorkData" of the Statusing web service seems to be
correct. Does anybody have an example to use this method to write
"time phased data"?
Thanks in advance.
Regards,
Gernot Mulisch
maybe I did a mistake when asking for help for writing "working data"
into an assignment and I really meant "time phased data". So I wanna
be more precise and would like to ask you for help to write time
phased data into assignments.
An example: I create an assignment with work = 0h and in a second step
I want to set work from March 12th to 16th and March 26th to 30th with
8h per day. After studying the SDK I found that the method
"SetAssignmentWorkData" of the Statusing web service seems to be
correct. Does anybody have an example to use this method to write
"time phased data"?
Thanks in advance.
Regards,
Gernot Mulisch