R
Rob
Hi,
I am running MS Project 2003 sp1 (via Project Server) with Solomon 5.5 PSA
enabler. After a simple quick customization to edit the EnterpriseNumber1
field, all of my "Actual Work" values are now zero. It seems like MS Project
is no longer going back to Solomon to get the actual hours. I have removed my
customization and it has had no effect.
Anyone have any ideas?
I am running MS Project 2003 sp1 (via Project Server) with Solomon 5.5 PSA
enabler. After a simple quick customization to edit the EnterpriseNumber1
field, all of my "Actual Work" values are now zero. It seems like MS Project
is no longer going back to Solomon to get the actual hours. I have removed my
customization and it has had no effect.
Anyone have any ideas?