projectserverdragon
OK here's a goodie...
I am in strategic planning mode for 2011 and have defined our portfolio of
initiatives. I am now defining all assignments and have found that Project
Server is not utilizing the availability which I have defined for that time
period. It seems to be defining availability based on current date instead
of what I have slated for next year.
i.e John Doe is slated as follows:
01/01/10-12/31/10 - 80%
01/01/11-06/30/11 - 50%
07/01/11-12/31/11 - 75%
So as you may know all of John Doe's 2011 work is getting allocated at the
80% instead of the desired 50% & 70%
If this is standard then how would one be able to accomplish a forcast as
such?
I am in strategic planning mode for 2011 and have defined our portfolio of
initiatives. I am now defining all assignments and have found that Project
Server is not utilizing the availability which I have defined for that time
period. It seems to be defining availability based on current date instead
of what I have slated for next year.
i.e John Doe is slated as follows:
01/01/10-12/31/10 - 80%
01/01/11-06/30/11 - 50%
07/01/11-12/31/11 - 75%
So as you may know all of John Doe's 2011 work is getting allocated at the
80% instead of the desired 50% & 70%
If this is standard then how would one be able to accomplish a forcast as
such?