I have encountered an inconsistency w/ submitted status of timesheets.


Issue #1

1. Resource A submits timesheet for week 1.
2. (Now in Week 2) Resource A now shows that the timesheet has not been
submitted for week 1 on their Home Page .
3. Resource Manager also shows the timesheet as unsubmitted for week 1.

I went into timesheet and clicked Update All and received the correct
message that no changes are available for update which proves that it was
actually submitted.

Why is the submitted status not updated for Resource A?
 