T
Timo Lenz
Hi,
i'm using psi to create tasks in an existing enterprise project. All works
well, if i use the AddPositionType.Last, but, if I use AddPositionType.middle
and set the AddAfterTaskUid I get an PSI error after 30 to 40 tasks !?
Do anybody know something about this?
i'm using psi to create tasks in an existing enterprise project. All works
well, if i use the AddPositionType.Last, but, if I use AddPositionType.middle
and set the AddAfterTaskUid I get an PSI error after 30 to 40 tasks !?
Do anybody know something about this?