PSI Baseline Data

B

Bryant Likes

Is the only baseline data available via the PSI the tb_* columns? In project
there are 11 possible baselines so I was just wondering if I only have
access to the latest one.

Thanks!
 
G

Guest

Hello Bryant,

Sorry....

In the Project 2007 SDK section "Project Server Programmibility"
under the heading "What the PSI does not do" you will find the following:

Baselines and Earned Value
Saving a baseline or editing baseline data.
Setting a progress date.
Calculating variance and earned value.

Bob
 
B

Bryant Likes

Hello Bryant,

Sorry....

In the Project 2007 SDK section "Project Server Programmibility"
under the heading "What the PSI does not do" you will find the following:

Baselines and Earned Value
Saving a baseline or editing baseline data.
Setting a progress date.
Calculating variance and earned value.

Thanks Bob.

Does anyone know what the values that are included in the PSI refer to?
There are baseline values, but I'm just not clear on what populates them.

Thanks!
 
B

Bryant Likes

Hello Bryant,

Sorry....

In the Project 2007 SDK section "Project Server Programmibility"
under the heading "What the PSI does not do" you will find the following:

Baselines and Earned Value
Saving a baseline or editing baseline data.
Setting a progress date.
[snip]

Just to be clear, are the Baselines 1-10 considered progress dates?

The client really wants to view this data but it seems I can only access it
via project client. Is this true?

Thanks!
 