Roy G
All,
When retrieving data using PSI, once the task start or finish date are after
the day our clock changes to 'Summer Clock', I recieve an extra hour on that
datetime. For example: if the Daylight Saving changes on 28.3 and I have a
task starting on 27.03 08:00 and ending on 01.04 17:00, when I use PSI to
read it I get 27.03 08:00 - 01.04 18:00.
Do I need to take care of that difference? obviously the Project
Professional does.
Thanks,
Roy