Hi,
How do you update the timephased cost information for a cost resource using
the PSI?
--I don't see a PID value for updating cost information in the Statusing Web
Service, so I don't see how I can do it there.
--I've tried just setting the ASSN_COST value when adding a new assignment
row using the AddToProject method of the Project Web Service, but the cost
values always show up with a 0.
--This is a cost resource, so entering values in a work field doesn't seem
appropriate.
What's a programmer to do?
Thanks for the help.
How do you update the timephased cost information for a cost resource using
the PSI?
--I don't see a PID value for updating cost information in the Statusing Web
Service, so I don't see how I can do it there.
--I've tried just setting the ASSN_COST value when adding a new assignment
row using the AddToProject method of the Project Web Service, but the cost
values always show up with a 0.
--This is a cost resource, so entering values in a work field doesn't seem
appropriate.
What's a programmer to do?
Thanks for the help.