P
ProjectBob
Hi,
I have used UpdateResources to update an enterprise material resource
RES_STD_RATE. Once the update completes the dataset shows the new value, the
published Resources table in SQL shows the updated value, and when you view
the resource in the resource centre in PWA it shows the updated value.
However, if I then open the resource in Project it shows the old resource
value, and likewise when I open a plan that uses the resource they show the
old value also. Is there a step I have to use after the UpdateResources to
make sure that the resource global is updated which filters down into all
plans?
Thanks
I have used UpdateResources to update an enterprise material resource
RES_STD_RATE. Once the update completes the dataset shows the new value, the
published Resources table in SQL shows the updated value, and when you view
the resource in the resource centre in PWA it shows the updated value.
However, if I then open the resource in Project it shows the old resource
value, and likewise when I open a plan that uses the resource they show the
old value also. Is there a step I have to use after the UpdateResources to
make sure that the resource global is updated which filters down into all
plans?
Thanks