B
Bryant Likes
Okay so I knew that the events that were called were different between the
two.
Project Update -> Project Saved Event
PSI Update -> Project Updating Event, Project Saved Event, Project Updated
Event
But something that doesn't make sense to me the that if you update a project
via the project client the project's mod_rev_counter in the msp_projects
table gets incremented as well as the task's mod_rev_counter. However, if
you make the same change via the PSI only the task's mod_rev_counter gets
incremented. Not a huge deal but causing me some headaches when tracking PSI
updates.
Is this by design or is it a bug of some sort?
two.
Project Update -> Project Saved Event
PSI Update -> Project Updating Event, Project Saved Event, Project Updated
Event
But something that doesn't make sense to me the that if you update a project
via the project client the project's mod_rev_counter in the msp_projects
table gets incremented as well as the task's mod_rev_counter. However, if
you make the same change via the PSI only the task's mod_rev_counter gets
incremented. Not a huge deal but causing me some headaches when tracking PSI
updates.
Is this by design or is it a bug of some sort?