A
Ali Aziz
Hi,
We're starting a customer project and wanted to confirm a few things on the
capability of the Project Server Interface web services before we began. The
following points set the context:
* We will create a project in MS Project and publish it on the Project Server
* Say, the project has 6 phases, each phase has 1 task line and 1 milestone
line
* We want to allow project team members to submit time against the tasks via
SMS (text message). We already use a web services enabled SMS gateway so are
able to receive SMSs. Once the SMS is received, we imagine the TimeSheet
webservice and its operations will allow us to update a particular task line
e.g. put percentage complete to 100%. Is this assumption correct?
* We are using an external BPM platform that maps the 6 phases of the
project into a workflow with 6 milestone/tollgate steps. Each time a
milestone/tollgate step is approved in the workflow, we want to update the
milestone step within the project, so that when the project is opened again
in MS Project, the milestone appears as 100% completed. We imagine the
Project webservice and its operations will allow us to update a particular
milestone line e.g. put percentage complete to 100%. Is this assumption
correct?
Would really appreciate any pitfall warnings etc. before we embark on this
effort. Also an indication of API operations to call and and any "setup"
calls to make before invoking other operations e.g. authentication/login
calls etc.
Thanks in advance,
--Ali Aziz
We're starting a customer project and wanted to confirm a few things on the
capability of the Project Server Interface web services before we began. The
following points set the context:
* We will create a project in MS Project and publish it on the Project Server
* Say, the project has 6 phases, each phase has 1 task line and 1 milestone
line
* We want to allow project team members to submit time against the tasks via
SMS (text message). We already use a web services enabled SMS gateway so are
able to receive SMSs. Once the SMS is received, we imagine the TimeSheet
webservice and its operations will allow us to update a particular task line
e.g. put percentage complete to 100%. Is this assumption correct?
* We are using an external BPM platform that maps the 6 phases of the
project into a workflow with 6 milestone/tollgate steps. Each time a
milestone/tollgate step is approved in the workflow, we want to update the
milestone step within the project, so that when the project is opened again
in MS Project, the milestone appears as 100% completed. We imagine the
Project webservice and its operations will allow us to update a particular
milestone line e.g. put percentage complete to 100%. Is this assumption
correct?
Would really appreciate any pitfall warnings etc. before we embark on this
effort. Also an indication of API operations to call and and any "setup"
calls to make before invoking other operations e.g. authentication/login
calls etc.
Thanks in advance,
--Ali Aziz