We recently selected the Publish All Information button on a new version of a
previously imported project plan. This plan had tasks that had been worked
on previously, with team members logging actual hours against some of the
tasks. After publication, some team members could see all their tasks in PWA
and others could not. We selected one of the resources that could not see
all of his tasks, republished his assignments, and the previously missing
tasks showed up in PWA as new tasks. Has anyone else run into this? We are
planning to republish all assignments one resource at a time because we don't
trust the Publish All Information button...
previously imported project plan. This plan had tasks that had been worked
on previously, with team members logging actual hours against some of the
tasks. After publication, some team members could see all their tasks in PWA
and others could not. We selected one of the resources that could not see
all of his tasks, republished his assignments, and the previously missing
tasks showed up in PWA as new tasks. Has anyone else run into this? We are
planning to republish all assignments one resource at a time because we don't
trust the Publish All Information button...