Publish Erorr

I

Iranian Realman

I have a problem with my Microsoft Project 2003, I used to see an Icon that
the tip of "Information for this taskj has changed. select publish new and
changed assignment to update the resources" when i did any change on Plan
Information, the Icon looked like an yellow Envelope that had an red "!" mark
in its right hand. but at the moment when I do any change on my plan there is
no Icon in Information column.

thanks a lot.
 
D

Dale Howard [MVP]

Iranian Realman --

If you wish to see the indicator whenevery you make ANY change in the
project, complete the following steps:

1. Open the project in question
2. Click Tools - Options - Collaborate
3. Select the "Any task changes" option in the middle of the dialog
4. Click the "Set as Default" button
5. Click OK

Hope this helps.
 
I

Iranian Realman

hi

thanks Dale,i did that but it wasn't usefull, in the other hand the problem
is that i can't publish changed tasks properly, when i publish the plan,
tasks in "Projects Pane" in "MS Proj. Web Aceess" apear, but they don't
apear in "Tasks Pane" of every resource.

In resource's Task pane in web acceess just "their self created tasks" exist
and tehy can't see their tasks in their task pane.

thanks
 