Hello,
A few changes (%complete, Actual Finish Date) were made
to 6 tasks in a project plan. The Project Manager then
Saved/Collorobate/Publish All Information.
The problem is the icon (envelope !)indicator that tells
one that task information has changed so select publish
New and Changed assignments still appears.

The %complete change seem to take; however, the dates
were not. When the Project Manager trys to publish again
an message appears saying there are no changes.

Any ideas? Has anyone seen this problem?
Note: We always use Publish All Information per
Microsoft.

Thanks in advance,
RhondaL
 
G

Gary L. Chefetz \(MVP\)

Rhonda:

The affect of doing this varies by tracking method, which you don't specify.
You may need to republish these tasks and select to overwrite actual work
when doing so.

--

Gary L. Chefetz, MVP
"We wrote the book on Project Server
http://www.msprojectexperts.com

-
 