Hello,
We are using Project Server with a good quantity of projects to manage
at the same time. To manage all the cross-link between projects, we
created a Master Project.
So in the case that our Master Project contains about 20 projects all
interlinked, as soon as we change the first project duration, the 19
others are also modified and we need to republish all Assignment for
all of them.
We have tried to use the View Populator tool from Microsoft but it only
publish the project plan without the Assignment modifications.
Except for opening all 20 projects and manually publish New & Changed
assignment, what would be the best way to handle this issue and make it
faster to update assignments?
Thanks for your help.
Eric Doucet
We are using Project Server with a good quantity of projects to manage
at the same time. To manage all the cross-link between projects, we
created a Master Project.
So in the case that our Master Project contains about 20 projects all
interlinked, as soon as we change the first project duration, the 19
others are also modified and we need to republish all Assignment for
all of them.
We have tried to use the View Populator tool from Microsoft but it only
publish the project plan without the Assignment modifications.
Except for opening all 20 projects and manually publish New & Changed
assignment, what would be the best way to handle this issue and make it
faster to update assignments?
Thanks for your help.
Eric Doucet