K
Kathy S
Using Project Server 2003 with MSP Professional 2003.
We have a handful of projects where the "Information for this task has
changed. Select Publish New and Changed Assignments to update the
resources." icon on the Task Sheet won't go away no matter how many
times the project is published using the different publishing
options. The information is not being updated in PWA Task page;
however, if I choose Republish Assignments - Overwrite actual work
entered by resources, PWA is updated but the icon still appears.
MSP's Tools - Options - Collaborate, is Any task information changes &
New and Changed Assignments. Multiple PMs have the same problem. Any
suggestions?
Thanks,
Kathy
We have a handful of projects where the "Information for this task has
changed. Select Publish New and Changed Assignments to update the
resources." icon on the Task Sheet won't go away no matter how many
times the project is published using the different publishing
options. The information is not being updated in PWA Task page;
however, if I choose Republish Assignments - Overwrite actual work
entered by resources, PWA is updated but the icon still appears.
MSP's Tools - Options - Collaborate, is Any task information changes &
New and Changed Assignments. Multiple PMs have the same problem. Any
suggestions?
Thanks,
Kathy