P
Paul Linscott
Question 1
Is there a way to see the publish status of a project in PWA i.e.
Published - tasks that have been assigned to resources
Published (saved) - project just saved in the DB - tasks have not been
assigned
There is a "last published" field, but this shows me the date when the
project was saved and/or published. Seems MS does not make a distinction
between a saved project and a true published project.
Question 2
What does the Collaborate/Publish/All Information do? Does it perform both
New and changed assignments and Project plan? It appears that the All
Information
takes the system must less time to perform this task than it does for the
New and Changed Assignments - both projects used were identical and no one
was on the test system at the time of the test.
thx
Paul
Is there a way to see the publish status of a project in PWA i.e.
Published - tasks that have been assigned to resources
Published (saved) - project just saved in the DB - tasks have not been
assigned
There is a "last published" field, but this shows me the date when the
project was saved and/or published. Seems MS does not make a distinction
between a saved project and a true published project.
Question 2
What does the Collaborate/Publish/All Information do? Does it perform both
New and changed assignments and Project plan? It appears that the All
Information
takes the system must less time to perform this task than it does for the
New and Changed Assignments - both projects used were identical and no one
was on the test system at the time of the test.
thx
Paul