M
Mike F
Has anyone seen this? I published a project and compared the hours in PWA to
the hours in Project and they do not match...for example:
Remaining hours:
in PWA = 1423.25
in MSP = 1423.24
I open the project from PWA into Project and the difference exists. I know
it is not a big differnce, but I have to explain it to my customer why the
difference exists. Is it a decimal calculation differnece between the fields?
the hours in Project and they do not match...for example:
Remaining hours:
in PWA = 1423.25
in MSP = 1423.24
I open the project from PWA into Project and the difference exists. I know
it is not a big differnce, but I have to explain it to my customer why the
difference exists. Is it a decimal calculation differnece between the fields?