Publishing a project adds 7 days to SOME durations

J

jlbreyer

I have a 1202 line schedule developed in Pro 2003 - NOT connected to Project
Server. It has an overall duration of 1102 days. I publish it to the Server
after making sure the modified standard calendar is in the Global.mpt, and
the resulting published version has an overall duration of 1108 days. As an
example of an internal task problem, I have two tasks in the management
section that are level-of-effort tasks. They both have a duration of 782
days and started on 11/30/04. After publishing, one is unchanged, the other
has increased duration to 789 days and the finish has moved from 1/15/08 to
1/24/08.

Any ideas why this happens?
jlb
 