When I publish New and Changed Assignments the project's publish
date/time is not updated. This seems reasonable, since the project
many have not changed only the assignments, but also I noticed that the
changes I make to the assignments are also not published. That is the
resource's tasks don't change in PWA! At least they don't show up in
PWA views when I drill down on the project.
Is this the way Publish New and Changed Assignments should work? If it
is, why would I ever use it?
It looks like I need to aways use Publish All it I want the change to
show up in PWA view.
date/time is not updated. This seems reasonable, since the project
many have not changed only the assignments, but also I noticed that the
changes I make to the assignments are also not published. That is the
resource's tasks don't change in PWA! At least they don't show up in
PWA views when I drill down on the project.
Is this the way Publish New and Changed Assignments should work? If it
is, why would I ever use it?
It looks like I need to aways use Publish All it I want the change to
show up in PWA view.