Publishing Project Plan Error

  • Thread starter Week-end Work day Exceptions in EPM
  • Start date
W

Week-end Work day Exceptions in EPM

We have a project plan that has been published many times yet now is unable
as it get a 26000 error; Failed But Not Blocking Correlation

Error summary/areas:
Reporting message processor failed
ReportingProjectChangeMessageFailed
ReportingProjectChangeMessageFailed
ReportingProjectChangeMessageFailed
ReportingProjectChangeMessageFailed
ReportingProjectChangeMessageFailed
ReportingProjectChangeMessageFailed
Queue
GeneralQueueJobFailed
Error details:

<?xml version="1.0" encoding="utf-16"?>
<errinfo>
<general>
<class name="Reporting message processor failed">
<error id="24006" name="ReportingProjectChangeMessageFailed"
uid="01949c98-580e-469b-b871-b4b9ac077187" QueueMessageBody="Project
UID='367e1729-3e71-4af6-88be-ec7661d15d46'. PublishType='ProjectPublish'"
Error="The INSERT statement conflicted with the FOREIGN KEY constraint
"FK_MSP_EpmTaskBaseline_ProjectUID_TaskUID". The conflict occurred in
database "ProjectServer_Reporting_EPM", table "dbo.MSP_EpmTask".
The statement has been terminated." />
<error id="24006" name="ReportingProjectChangeMessageFailed"
uid="4f54a4b3-be57-43f1-a075-db84648fc3b7" QueueMessageBody="Project
UID='367e1729-3e71-4af6-88be-ec7661d15d46'. PublishType='ProjectPublish'"
Error="The INSERT statement conflicted with the FOREIGN KEY constraint
"FK_MSP_EpmTaskBaseline_ProjectUID_TaskUID". The conflict occurred in
database "ProjectServer_Reporting_EPM", table "dbo.MSP_EpmTask".
The statement has been terminated." />
<error id="24006" name="ReportingProjectChangeMessageFailed"
uid="6721de12-19bc-45a9-b006-76643ae2aba0" QueueMessageBody="Project
UID='367e1729-3e71-4af6-88be-ec7661d15d46'. PublishType='ProjectPublish'"
Error="The INSERT statement conflicted with the FOREIGN KEY constraint
"FK_MSP_EpmTaskBaseline_ProjectUID_TaskUID". The conflict occurred in
database "ProjectServer_Reporting_EPM", table "dbo.MSP_EpmTask".
The statement has been terminated." />
<error id="24006" name="ReportingProjectChangeMessageFailed"
uid="8e4dd7fa-7fa6-4a29-a8cb-943ab13f0065" QueueMessageBody="Project
UID='367e1729-3e71-4af6-88be-ec7661d15d46'. PublishType='ProjectPublish'"
Error="The INSERT statement conflicted with the FOREIGN KEY constraint
"FK_MSP_EpmTaskBaseline_ProjectUID_TaskUID". The conflict occurred in
database "ProjectServer_Reporting_EPM", table "dbo.MSP_EpmTask".
The statement has been terminated." />
<error id="24006" name="ReportingProjectChangeMessageFailed"
uid="30a1e442-29b2-4483-994b-1fdf56ac90f7" QueueMessageBody="Project
UID='367e1729-3e71-4af6-88be-ec7661d15d46'. PublishType='ProjectPublish'"
Error="The INSERT statement conflicted with the FOREIGN KEY constraint
"FK_MSP_EpmTaskBaseline_ProjectUID_TaskUID". The conflict occurred in
database "ProjectServer_Reporting_EPM", table "dbo.MSP_EpmTask".
The statement has been terminated." />
<error id="24006" name="ReportingProjectChangeMessageFailed"
uid="512f2413-4cb4-460a-b6ff-ea80f1cbb8cc" QueueMessageBody="Project
UID='367e1729-3e71-4af6-88be-ec7661d15d46'. PublishType='ProjectPublish'"
Error="The INSERT statement conflicted with the FOREIGN KEY constraint
"FK_MSP_EpmTaskBaseline_ProjectUID_TaskUID". The conflict occurred in
database "ProjectServer_Reporting_EPM", table "dbo.MSP_EpmTask".
The statement has been terminated." />
</class>
<class name="Queue">
<error id="26000" name="GeneralQueueJobFailed"
uid="956614d8-3d3d-410b-b69a-82e175c5dd42"
JobUID="8441ed1d-8256-41b9-bcbf-dd2b8c196528" ComputerName="EPMPROD"
GroupType="ReportingProjectPublish"
MessageType="ReportProjectPublishMessageEx" MessageId="1" Stage="" />
</class>
</general>
</errinfo>

We've tried republishing and it still does not work. Any suggestions as we
are at a loss.

Thank you.
 
W

Week-end Work day Exceptions in EPM

We've also rebuilt the reporting db and still get the error.

Thanks
 
G

Gary Chefetz

How do your users add resources to tasks? Do they ever use the resource
column in the Gantt chart. If so, are they changing from one resource to the
other using the resource column selector?



"Week-end Work day Exceptions in EPM"
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top