Hi there,
We've a problem in publishing a project from Project
Professional when it has got out of sync actuals.
When we adjust the actuals in Project Web access, it
works fine. But when we adjust it using Project
Professional, and try to publish it, we get this error.
We are fine not to use Project Professional for updation.
But when we use Project Professional to publish, we'll
get a dialog when we open the project for next time in
Project Professional from PWA, asking if we want to sync
the actuals: if we accept it; we lose all the actuals in
the project (Replaces all the values in PWA Data base).
But people who'll be using this one could use project
professional and that's why we want people not to face
this problem at all.
Is there any way to disable that dialog which prompts
to over write the actuals with PWA actuals, as the
default choice is "Yes", which will remove all the
actuals?
BTW, we are using only enterprise resources, not any
local resources at all.
Thanks,
Pavi
We've a problem in publishing a project from Project
Professional when it has got out of sync actuals.
When we adjust the actuals in Project Web access, it
works fine. But when we adjust it using Project
Professional, and try to publish it, we get this error.
We are fine not to use Project Professional for updation.
But when we use Project Professional to publish, we'll
get a dialog when we open the project for next time in
Project Professional from PWA, asking if we want to sync
the actuals: if we accept it; we lose all the actuals in
the project (Replaces all the values in PWA Data base).
But people who'll be using this one could use project
professional and that's why we want people not to face
this problem at all.
Is there any way to disable that dialog which prompts
to over write the actuals with PWA actuals, as the
default choice is "Yes", which will remove all the
actuals?
BTW, we are using only enterprise resources, not any
local resources at all.
Thanks,
Pavi