M
MichaelDBang
Hello,
I currently have Project Server setup to calculate % of task done based off
of actual work and work remaining.
However, right now I have to:
1) Enter in my timesheet hours under Timesheet tab.
2) Update the Actual Work in Task Management tab.
I'm wondering if there's a way to have Project calculate Actual Work from
the hours entered in Timesheet? Would be nice.
Thank you!
Michael
I currently have Project Server setup to calculate % of task done based off
of actual work and work remaining.
However, right now I have to:
1) Enter in my timesheet hours under Timesheet tab.
2) Update the Actual Work in Task Management tab.
I'm wondering if there's a way to have Project calculate Actual Work from
the hours entered in Timesheet? Would be nice.
Thank you!
Michael