Pulling Base Daily hours for each Employee

S

SophiaNicole

I have two offices, in which one works 40 base hours per week and the other
works 37.5 base hours per week. I am working on a project where I need to
pull base hours for each employee. What tables do I pull this information
from? What are the table names and the column names? I'm new to this so if
I'm not being clear please let me know.
 
G

Gary L. Chefetz [MVP]

SK:

This information is stored in the resource calendars, which are accessible
through the Project API. It's not stored in the database.
 
S

SophiaNicole

Thanks!
--
SK


Gary L. Chefetz said:
SK:

This information is stored in the resource calendars, which are accessible
through the Project API. It's not stored in the database.
 
N

nakiefer

Gary,

could you elaborate on this? If I have situation wher I have a shared
resource file and want to work on that information for all projects from with
vba how would I go about doig that
 
S

SophiaNicole

Gary,

Could you elaborate on this? If I have a situation where I have a shared
resource file and want to work on that information for all projects from
with in
vba how would I go about doing that?
 