Pulling data into published schedule

M

Muozo

Is there a way to write a VBA macro to pull data such as % complete, start,
and finish fields from an .mpp project file into a published schedule?

Thank you in advance.
 
R

Rod Gill

Yes. Safest way is to open both projects using automation then do the
updates. Finally save then publish the project server project.
 