B
Bill Meacham
How can I "push" task information from one project to another? Here is what
my client wants:
1) An end user updates the finish date (scheduled finish date or actual
finish) of a task in project A.
2) This triggers an update to the scheduled finish date of a task in
project B.
I know you could do this by including project A in project B as an included
subproject, but there are reasons we do not want to do that in Project
Server. Is there any other way to do it?
my client wants:
1) An end user updates the finish date (scheduled finish date or actual
finish) of a task in project A.
2) This triggers an update to the scheduled finish date of a task in
project B.
I know you could do this by including project A in project B as an included
subproject, but there are reasons we do not want to do that in Project
Server. Is there any other way to do it?