R
Rob
Approving a timesheet simply approves the time entered in the timesheet.
Approving a task update actually transfers the task progress into the
appropriate Microsoft Project plans.
Can you eliminate the step of going through the My tasks and have the
timesheet directly [after approval] push the hours to the plan?
Why the extra step in 2007 from 2003?
Approving a task update actually transfers the task progress into the
appropriate Microsoft Project plans.
Can you eliminate the step of going through the My tasks and have the
timesheet directly [after approval] push the hours to the plan?
Why the extra step in 2007 from 2003?