Pushing "% Work Complete" in Timesheet view

J

Joe

I have the field “% Work Complete†on the timesheet view in PWA. When
resource submits their actual hours and the task is complete. This field is
not updated when I perform a “publish all†after accepting the updates to the
server. Do I have to do a “Re-publish†in order to “push†the updated “%
Work Compete†into the timesheet view ? I hate having to do this because now
everyone will always have “new†task assignments every time I do a re-publish
to the plan. But I need to have the “% Work Complete†be accurate. Or am I
missing something here?
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top