I have about 23 small projects. In each project there are 3 phases
with about 10 tasks in each phase. Phase 1 works on a defined
start-end schedule date while Phase 2 has to wait on approval of Phase
1 (which could be days/weeks/months). How can I put that phase (and
all the tasks that depend on it) on hold?
To complicate matters, I have one project that links to all of the
smaller projects and from time to time I need to put an entire project
on hold with no definite start date. Is there a way to put an entire
project on hold?
with about 10 tasks in each phase. Phase 1 works on a defined
start-end schedule date while Phase 2 has to wait on approval of Phase
1 (which could be days/weeks/months). How can I put that phase (and
all the tasks that depend on it) on hold?
To complicate matters, I have one project that links to all of the
smaller projects and from time to time I need to put an entire project
on hold with no definite start date. Is there a way to put an entire
project on hold?