PWA 2003 enter times on behalf of another user

E

Elsa L.

Hello,
is it possilble with Project Server Web Access 2003 to insert actual work on
behalf of another user (Tasks tab).

I know that in 2007 there is the notion of surrogate timesheets that is
something near what I need, but is there any soluiton for 2003?

Thank you in advance,
Elsa
 
M

Marc Soester [MVP]

Sorry Elsa, that is not possible, you will need to re-assing the tasks to
someone else. The "surregate timesheet" functionality does not exist in 03
 
E

Elsa L.

Not so good news :(
But Thanks Marc!
Elsa


Marc Soester said:
Sorry Elsa, that is not possible, you will need to re-assing the tasks to
someone else. The "surregate timesheet" functionality does not exist in 03
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top