G
Gary Zag
Under "Task Settings and Display" for "Define Current Tasks" there is one
setting for "or are not older than or further in the future more than __
days". Currently if you increase this from the default of 10 days to say 30
days you see completed tasks that are also 30 days old. It would be nice to
have two settings. One for future tasks and one for completed tasks that
could be set to a lower value.
----------------
This post is a suggestion for Microsoft, and Microsoft responds to the
suggestions with the most votes. To vote for this suggestion, click the "I
Agree" button in the message pane. If you do not see the button, follow this
link to open the suggestion in the Microsoft Web-based Newsreader and then
click "I Agree" in the message pane.
http://www.microsoft.com/office/com...b138e02980&dg=microsoft.public.project.server
setting for "or are not older than or further in the future more than __
days". Currently if you increase this from the default of 10 days to say 30
days you see completed tasks that are also 30 days old. It would be nice to
have two settings. One for future tasks and one for completed tasks that
could be set to a lower value.
----------------
This post is a suggestion for Microsoft, and Microsoft responds to the
suggestions with the most votes. To vote for this suggestion, click the "I
Agree" button in the message pane. If you do not see the button, follow this
link to open the suggestion in the Microsoft Web-based Newsreader and then
click "I Agree" in the message pane.
http://www.microsoft.com/office/com...b138e02980&dg=microsoft.public.project.server