S
ST
Hi,
I'm trying to enter a formula for a custom enterprise task flag in PWA 2007,
but I'm having problem with MS Project accepting/ validating it.
IIf((([Finish]>[Deadline]) And Not ([Deadline]="NA")) And (([Duration]>0) Or
([Duration9]>0)),True,False)
The problem is that it does not like the reference to [Duration9]. Can we
not use local custom fields in formulas?
/Spiro Theopoulos.
I'm trying to enter a formula for a custom enterprise task flag in PWA 2007,
but I'm having problem with MS Project accepting/ validating it.
IIf((([Finish]>[Deadline]) And Not ([Deadline]="NA")) And (([Duration]>0) Or
([Duration9]>0)),True,False)
The problem is that it does not like the reference to [Duration9]. Can we
not use local custom fields in formulas?
/Spiro Theopoulos.