PWA 2007: task split not shown in Project View

L

lhaker

Does anybody know, why task splits aren't shown anymore in PWA 2007
Project Gantt view? The splits have been shown in PWA 2003 Project
Gantt View, but within PWA 2007 i have found no way to show the
splits.

Lena Haker
 
J

Jonathan Sofer

Have you made sure that the option is turned on "Split in-progress tasks" is
enabled under Tools>Options under the Schedule tab?

Jonathan
 
L

lhaker

You are talking about the rendering of Project Pro Gantt Charts,
right? The issue is with the rendering of the Project Web Access Gantt
Chart (Projectdetails). The ActiveX Control under /PWA/
ProjectDrillDown.aspx doesn't show split-tasks.

Anybody any idea?

Lena
 
J

Jonathan Sofer

Sorry Lena,

I misread your initial post and didn't see that you were referring to the
Gantt view in PWA. I do not have any good answers for you other than it
seems that the split progress functionality has been removed in PWA 2007
ActiveX Control.

Jonathan
 