PWA 2007-Timesheet - Phantom Total Hours

J

Jan

For the last couple of weeks I have a resource that sees a Total for each day
of the week on their timesheet (after being created) when no hours have been
added/recorded. I've tried to see if it's being caused by a specific project
without any luck.

Has anyone else experienced this if so were you able to identify the
cause/solution and/or is it a known bug?
 
A

Ankit

We have been experiencing the similar errors. I have tried to look at
projects for which the time is populating automatically and the only thing I
have seen similar is that resources have been assigned to summary tasks.
However, I do not think this is related.

If anyone has some leads, it would greatlly help.
 
G

Gary Chefetz

You should never assign resources to summary tasks. They will inherit hours
from the subtasks and these will be double counted. Big, big mistake.
 