T
tilt
Project Pro 2003, Project Server 2003, PWA, Managed Time Periods.
We would like to temporarily prevent people from entering time when we
are making plan updates on the server. So we try to close the current
open time period and go ahead with making updates to the plan.
Unfortunately this does not seem to prevent people from still being
able to enter time for the current period (which is supposedly
closed).
Any ideas why this happens?
By the way, in our installation there are a lot of things in Project
and Project Server that do not work as they are supposed to work, so
this might be just one more case like that.
Cheers
We would like to temporarily prevent people from entering time when we
are making plan updates on the server. So we try to close the current
open time period and go ahead with making updates to the plan.
Unfortunately this does not seem to prevent people from still being
able to enter time for the current period (which is supposedly
closed).
Any ideas why this happens?
By the way, in our installation there are a lot of things in Project
and Project Server that do not work as they are supposed to work, so
this might be just one more case like that.
Cheers