PWA activity not auto populating

P

Penny

We recently implemented a project 07 server including project web access
(PWA). I am trying to create an activity or proposal in PWA. I enter all of
the required information in summary information and then begin entering
information on the work details screen. When I enter a new task, it should
populate with the line number 1,2,3, etc. and I cannot enter the number
manually. If I try to save the work details without the number assignment, I
receive the following error, "Failed to enable constraints. One or more rows
contain values violating non-null, unique, or foreign-key constraints."

Any assistance would be greatly appreciated.
 
J

John

Penny said:
We recently implemented a project 07 server including project web access
(PWA). I am trying to create an activity or proposal in PWA. I enter all of
the required information in summary information and then begin entering
information on the work details screen. When I enter a new task, it should
populate with the line number 1,2,3, etc. and I cannot enter the number
manually. If I try to save the work details without the number assignment, I
receive the following error, "Failed to enable constraints. One or more rows
contain values violating non-null, unique, or foreign-key constraints."

Any assistance would be greatly appreciated.

Penny,
Since this question is on Project Server, you will get a better response
if you post it to our sister newsgroup, microsoft.public.project.server.
This newsgroup is dedicated to the stand alone version of Project.

John