Frank Herber
Hi folks,
we're running a Project Server 2003 and have a test project saved so far.
Web Access is already implemented and works fine atm.
We plan to use PWA for most of the personel/ressources here but Project 2003
Pro is planned to be used by the project managers.
Now the question:
The ressources can't edit/change the actual work row in PWA. Editable are
the %work done and the total work rows where the calculation of the actual
work is made correctly.
Our personnel don't want to use the %work done as it is easier to track the
hours/work time itself in actual work.
Where have I to change this behavior or is it not possible to change that
for an existing project or in Project Server?
Regards
Frank
we're running a Project Server 2003 and have a test project saved so far.
Web Access is already implemented and works fine atm.
We plan to use PWA for most of the personel/ressources here but Project 2003
Pro is planned to be used by the project managers.
Now the question:
The ressources can't edit/change the actual work row in PWA. Editable are
the %work done and the total work rows where the calculation of the actual
work is made correctly.
Our personnel don't want to use the %work done as it is easier to track the
hours/work time itself in actual work.
Where have I to change this behavior or is it not possible to change that
for an existing project or in Project Server?
Regards
Frank