Hi all,
I was thinking to use only the generic resources to plan and track...
I was woundering if someone can give me some tips on this situation...
My project manager want to assign task to generic resources... and he
wants to track time against generic (so it can be easy the process of
tracking time...)
I don't need to use the timesheet and I just want to track the time
against the task (possibly in PWA)...
Is it possible to do this??? is it possible to track the generic
resources in PWA???
What about using the Team Assignement Pool????
any suggestion??
thanks lots all
cheers
Vit
I was thinking to use only the generic resources to plan and track...
I was woundering if someone can give me some tips on this situation...
My project manager want to assign task to generic resources... and he
wants to track time against generic (so it can be easy the process of
tracking time...)
I don't need to use the timesheet and I just want to track the time
against the task (possibly in PWA)...
Is it possible to do this??? is it possible to track the generic
resources in PWA???
What about using the Team Assignement Pool????
any suggestion??
thanks lots all
cheers
Vit