B
Bhavtosh
hello,
i've setup PWA on a moss server named S1 and i have another machine M1 in
the same network to access PWA site
on M1 i have project pro 2007 installed. to start i made resource list with
different roles on server in order to use it on M1
i made a sample project and upload it on pwa site. now here i want to know
more about;
1. as a manager when i open the project from pwa on the client machine im
able to update it but other project members cant see the changes provided
they are already added to that project?
2. how can i implement a workflow to that project so that project lead can
also edit the project?
3. is there a difference between pwa tasks and ms project tasks? if yes then
do co-relate them?
i've setup PWA on a moss server named S1 and i have another machine M1 in
the same network to access PWA site
on M1 i have project pro 2007 installed. to start i made resource list with
different roles on server in order to use it on M1
i made a sample project and upload it on pwa site. now here i want to know
more about;
1. as a manager when i open the project from pwa on the client machine im
able to update it but other project members cant see the changes provided
they are already added to that project?
2. how can i implement a workflow to that project so that project lead can
also edit the project?
3. is there a difference between pwa tasks and ms project tasks? if yes then
do co-relate them?