PWA crashed after site migration

  • Thread starter Claudio Hidetoshi
  • Start date
C

Claudio Hidetoshi

Hi, I'm running partial migration of my projects. Then some projects are in
Project Server 2007 and others are in Project Server 2003.

Project Server 2007 sites were migrated using this sintax:
"...\bin\stsadm -o restore -url http://epm2007/sites/projectserver_758
-overwrite"
.... and the sites were created normally.

When I was migrating another site I made a mistake, changing the word
"sites" to "pwa".
"...\bin\stsadm -o restore -url http://epm2007/pwa/projectserver_758
-overwrite"

When I try to access PWA site, the migrated site is showed to me.

I looked at WSS_Content database and all PWA sites (not migrated sites, but
the new sites) were deleted, and PWA was overwritten.

I tried to restore PWA site, but it didn't work. No action occur in Timer
Service status. And no event view is generated.

I tried to delete PWA site and create a new PWA site, but I have to create
new databases (draft, archive, published, Reporting), ignoring actual
projects data.

Is there a way to create a new PWA site preserving actual databases ?

Any help will be very aprecciated.

Cláudio Hidetoshi
Rio de Janeiro - Brazil
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top