G
Gertie
In PWA, I am trying to set up an Enterprise Custom Task Field to subtract a
baseline date [Baseline10 Finish] from the current finish date [Finish]. I
have set it up as follows:
Entity = Task
Type = Duration
Formula - [Baseline10 Finish]-[Finish]
I am able to save the formula and I have created a PWA Project view that
includes the new field. However, the column for the new field is blank
although the [Baseline10 Finish] field and the [Finish] field contain data.
What is going wrong, please?
baseline date [Baseline10 Finish] from the current finish date [Finish]. I
have set it up as follows:
Entity = Task
Type = Duration
Formula - [Baseline10 Finish]-[Finish]
I am able to save the formula and I have created a PWA Project view that
includes the new field. However, the column for the new field is blank
although the [Baseline10 Finish] field and the [Finish] field contain data.
What is going wrong, please?