B
Barak Bester
Hi,
When I log into PWA-->Server Settings--> Look & Feel --> Gantt Chart Formats, under several formats there are bars named "Slippage", "Delay", "Early Schedule" and "Late Schedule".
As we know, a bar should show a line between a Start Date and an End Date.
Does anyone understand what these bars use as Start Date and End Date?
Thanks,
Barak
Submitted via EggHeadCafe - Software Developer Portal of Choice
..NET Security [aPress]
http://www.eggheadcafe.com/tutorial...59-b07c-b83d902e72cc/net-security-apress.aspx
When I log into PWA-->Server Settings--> Look & Feel --> Gantt Chart Formats, under several formats there are bars named "Slippage", "Delay", "Early Schedule" and "Late Schedule".
As we know, a bar should show a line between a Start Date and an End Date.
Does anyone understand what these bars use as Start Date and End Date?
Thanks,
Barak
Submitted via EggHeadCafe - Software Developer Portal of Choice
..NET Security [aPress]
http://www.eggheadcafe.com/tutorial...59-b07c-b83d902e72cc/net-security-apress.aspx