Sean Stenlund
Please HELP,
The time-phased "actual work" and "protected actual work" are exactly the
same. Everything has published sucessfully. All actual work data is only
through the second week of July. The gantt in Project Professional has a
progress line on all tasks only to the second week in July. However, in PWA
the progress line extends out into November. This is occurring on some
projects (not all) and not for every task in the projects.
I created a new task in one of the projects and updated the actual work day
by day to the second week of July, published, saved, looked at it in PWA, and
it is fine the other tasks are still funky.
I've saved a plan to disk, deleted the published project, made sure that
actual work only extended into July, saved and published to the project
server, and in PWA it still goes out to November (except the new task).
Going crazy,
Sean Stenlund
The time-phased "actual work" and "protected actual work" are exactly the
same. Everything has published sucessfully. All actual work data is only
through the second week of July. The gantt in Project Professional has a
progress line on all tasks only to the second week in July. However, in PWA
the progress line extends out into November. This is occurring on some
projects (not all) and not for every task in the projects.
I created a new task in one of the projects and updated the actual work day
by day to the second week of July, published, saved, looked at it in PWA, and
it is fine the other tasks are still funky.
I've saved a plan to disk, deleted the published project, made sure that
actual work only extended into July, saved and published to the project
server, and in PWA it still goes out to November (except the new task).
Going crazy,
Sean Stenlund