J
Jay
Create a project and set "Hours of work done per period" under Collaboration
Options in the Project client.
Asign a task to yesrself
Report on the task
Go into PWA open the task
Click on Progress
You shouls see three areas to report, Work, Actual Work and Overtime.
How do you remove OVERTIME? We don’t use it, and it just adds confusion.
The Overtime option pops up when you click in the Progress column of any
task. Our current setup to track actual hours worked, a one-week grid pops
up when you click on the Progress column of a task right now that allows you
to enter hour amounts per day of that week. You can change weeks at the top.
It’s got a Work row which is the scheduled work for that day. Below that
there’s an Actual Work row where people enter the actual amount of time they
spent on that task for the day. Below that is an Overtime row that we never
make any use of. It’s writeable, but it’s confusing to everyone who enters
their time.
How do I remove it?
Options in the Project client.
Asign a task to yesrself
Report on the task
Go into PWA open the task
Click on Progress
You shouls see three areas to report, Work, Actual Work and Overtime.
How do you remove OVERTIME? We don’t use it, and it just adds confusion.
The Overtime option pops up when you click in the Progress column of any
task. Our current setup to track actual hours worked, a one-week grid pops
up when you click on the Progress column of a task right now that allows you
to enter hour amounts per day of that week. You can change weeks at the top.
It’s got a Work row which is the scheduled work for that day. Below that
there’s an Actual Work row where people enter the actual amount of time they
spent on that task for the day. Below that is an Overtime row that we never
make any use of. It’s writeable, but it’s confusing to everyone who enters
their time.
How do I remove it?