PWA My Tasks and Tasks Updates not quite right when...

A

anovak

Occasionally I will enter hours worked and remaining hours, then the
forecasted finish is not correct. It may be off by several days.

I'll just change the forecast date directly and let PWA / My Tasks
adjust the Remaining Hours. And it appears to make sense once the
recalc is done.

However when I accept the updates and open the project , the forecast
date change does NOT flow down the rest of the schedule until I
deliberately hit F9 (refresh).

Is this a bug?? Any and all comments, suggestions, etc. would be
appreciated.

Thanks,
Andy Novak
UNT
 
B

Ben Howard

Hi Andy, have you got Automatic Recalc set within the Project Options window?
 
A

anovak

Hi Andy, have you got Automatic Recalc set within the Project Options window?

Yes, automatic. Any schedule changes seem to take effect until it
reaches the point of where the forecasted finish is changed directly
in PWA
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top